White County, SR-111 (Spencer Hwy.) repair of bridge over Calfkiller River (LM 6.37) in Sparta: Work on this project continues. The contractor has completed full depth deck repairs and will be completing work on expansion joints for Phase 2 construction. Sandblasting and painting operations within the middle span of the bridge are underway. Temporary traffic control signs are installed providing lane shifts to the outside lanes in both directions as Phase 2 progresses. All motorists should use extreme caution and be alert to construction equipment and vehicles on the project. The contractor may have short term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as necessary. Estimated project completion date is August 2015. [Mid-State Construction Co, Inc./Sorrelle/CNN292]